Lot Sizing Methods in MRP: Lot-for-Lot, EOQ, POQ, and More
Lot sizing decides how much to order or make each time. MRP works out what is needed and when. The lot sizing rule turns those net requirements into actual order quantities, and in doing so it sets how often you order, how much inventory you carry, and how many setups the plant runs.
There is no single best rule. Ordering exactly what is needed keeps inventory at zero and maximizes the number of orders. Ordering in large fixed quantities does the opposite. The right choice depends on the item: what it costs to order or set up, what it costs to hold, and how steady its demand is.
This guide explains the main lot sizing methods, compares them on the same demand with a worked example, and covers order modifiers, multi-level effects, and how to choose a rule for each kind of item.
What Is Lot Sizing?
Lot sizing is the rule a planning system uses to convert net requirements into planned order quantities. A lot is the quantity ordered from a supplier or produced on one work order. Every lot sizing method is a trade between two costs:
- Ordering or setup cost, which is paid once per order regardless of quantity: the purchase order, receiving, and inspection for a bought part, or the changeover for a made part
- Holding cost, which is paid on every unit for as long as it sits in stock: capital, space, insurance, handling, and the risk of obsolescence
Larger lots mean fewer orders and more inventory. Smaller lots mean the reverse. For where lot sizing sits in the planning run, see how MRP calculates requirements.
The Main Lot Sizing Methods
| Method | How the quantity is set | Best fit |
|---|---|---|
| Lot-for-lot (L4L) | Order exactly the net requirement of each period | Expensive items, make-to-order work, low setup cost |
| Fixed order quantity (FOQ) | Order the same quantity every time, or a multiple of it | Items bound by a pack, pallet, batch, or tooling quantity |
| Economic order quantity (EOQ) | A fixed quantity calculated to balance ordering and holding cost | Steady, continuous demand |
| Period order quantity (POQ) | Order enough to cover a fixed number of periods | Uneven demand, where a fixed quantity leaves remnants |
| Fixed period requirements | Same as POQ, with the number of periods set by policy, such as one month of supply | Low-value items ordered on a calendar |
| Dynamic methods | Calculate each order from the costs of the requirements ahead: least unit cost, least total cost, part period balancing, Wagner-Whitin | Lumpy demand where cost matters enough to justify the complexity |
The Cost Formulas
Total cost = (Number of orders × Cost per order) + (Units carried × Holding cost per unit per period)
Units carried is the sum of ending inventory across the periods.
Holding cost per unit per period = Unit cost × Annual carrying rate ÷ Periods per year
A part that costs $208 with a 25% annual carrying rate costs $52 a year to hold, or $1.00 per week.
EOQ = √(2 × Demand per period × Cost per order ÷ Holding cost per unit per period)
POQ interval = EOQ ÷ Average demand per period, rounded to a whole number of periods
For the derivation and limits of the first formula, see our guide to economic order quantity.
Worked Example: Four Methods on the Same Demand
MRP shows these net requirements for a part over the next six weeks. Each order costs $120 to place or set up, and holding a unit costs $1.00 per week. Nothing is on hand at the start.
| Week | 1 | 2 | 3 | 4 | 5 | 6 | Total |
|---|---|---|---|---|---|---|---|
| Net requirement | 40 | 60 | 30 | 80 | 50 | 70 | 330 |
Lot-for-lot. Six orders, one per week, each for exactly the requirement. Nothing is carried. Cost = 6 × $120 = $720
Fixed order quantity, using EOQ. Average demand is 330 ÷ 6 = 55 per week. EOQ = √(2 × 55 × $120 ÷ $1.00) = √13,200 = 114.9, rounded to 115.
| Week | 1 | 2 | 3 | 4 | 5 | 6 |
|---|---|---|---|---|---|---|
| Net requirement | 40 | 60 | 30 | 80 | 50 | 70 |
| Order received | 115 | 115 | 115 | |||
| Ending inventory | 75 | 15 | 100 | 20 | 85 | 15 |
Three orders, and 310 units carried across the six weeks. Cost = (3 × $120) + (310 × $1.00) = $670. Notice the remnants: 15 or 20 units are left over before each new order arrives, because a fixed quantity does not line up with uneven requirements.
Period order quantity. The interval is 115 ÷ 55 = 2.1, rounded to 2 weeks. Each order covers exactly two weeks of requirements.
| Week | 1 | 2 | 3 | 4 | 5 | 6 |
|---|---|---|---|---|---|---|
| Net requirement | 40 | 60 | 30 | 80 | 50 | 70 |
| Order received | 100 | 110 | 120 | |||
| Ending inventory | 60 | 0 | 80 | 0 | 70 | 0 |
Three orders again, but only 210 units carried, because there are no remnants. Cost = (3 × $120) + (210 × $1.00) = $570
A dynamic method. Testing every combination of order weeks, which is what the Wagner-Whitin method does, finds the lowest-cost plan: order 130 in week 1 to cover weeks 1 through 3, 130 in week 4 to cover weeks 4 and 5, and 70 in week 6. That is three orders and 170 units carried. Cost = (3 × $120) + (170 × $1.00) = $530
| Method | Orders | Units carried | Order cost | Holding cost | Total |
|---|---|---|---|---|---|
| Lot-for-lot | 6 | 0 | $720 | $0 | $720 |
| Fixed order quantity (115) | 3 | 310 | $360 | $310 | $670 |
| Period order quantity (2 weeks) | 3 | 210 | $360 | $210 | $570 |
| Dynamic (lowest cost) | 3 | 170 | $360 | $170 | $530 |
The ranking depends entirely on the two costs. If the order cost were $20 in place of $120, lot-for-lot would cost 6 × $20 = $120 and beat every other method. That is why reducing setup time matters so much: it makes small lots affordable.
Order Modifiers: Minimum, Maximum, and Multiple
Whatever the rule calculates, real constraints adjust it. Planning systems apply these as order modifiers:
- Minimum: the smallest quantity a supplier will sell or the plant will run
- Multiple: the quantity must be a multiple of a pack, pallet, coil, or batch size
- Maximum: the largest quantity allowed in one order, limited by storage, shelf life, or equipment
Example: the rule calls for 130 units. The supplier’s minimum is 100 and the part ships in cases of 50. The order becomes 150, the next multiple of 50 at or above 130. The extra 20 units carry into the following periods and reduce the next net requirement.
Modifiers are a common source of excess stock. A minimum that made sense when demand was high can leave a year of supply on the shelf after demand falls. See how to calculate safety stock for the other planning parameter that quietly adds inventory.
Lot Sizing Across BOM Levels
Lot sizes at one level become the requirements of the level below. If a finished item with steady demand of 55 a week is made in lots of 115, its components see demand of 115, then nothing, then 115. Each level of lot sizing makes demand lumpier for the levels beneath it and adds inventory to the system.
Two practical consequences follow. First, lot-for-lot is often the best rule for subassemblies and intermediate items, with larger lots reserved for purchased parts and items with a real setup cost. Second, dynamic methods recalculate order quantities whenever requirements change, which can reshuffle the orders below them. That instability is sometimes called nervousness, and it is one reason many planners prefer simpler rules. See the master production schedule, which uses time fences to keep near-term plans stable.
How to Choose a Lot Sizing Rule
- High-value items and make-to-order work: lot-for-lot. Carrying cost dominates and there is no reason to hold stock ahead of demand.
- Items with a significant setup or order cost and uneven demand: period order quantity. It cuts the number of orders without leaving remnants.
- Items with steady demand: EOQ, or a fixed quantity near it.
- Items bound by a physical quantity: a fixed quantity or a multiple. A batch tank, a heat-treat load, or a full pallet sets the lot.
- Low-value, high-volume items: a fixed period of supply, such as one month, or a reorder point. The planning effort is worth more than the inventory.
- Short shelf life: lot-for-lot or a short period of supply with a maximum, so stock does not expire.
Review the rules as well as the quantities. An item’s demand pattern, cost, and supplier terms change, and a rule set at implementation is rarely still right years later.
Common Mistakes
- Using one lot sizing rule for every item
- Applying EOQ to lumpy demand, where its assumption of steady usage does not hold
- Running large lots to make machine utilization look good while inventory builds
- Ignoring holding cost because it never appears on an invoice
- Leaving supplier minimums and multiples in the system after terms or demand have changed
- Lot sizing every level of the bill of materials, which multiplies inventory and lumpiness
- Treating setup cost as fixed and never working to reduce it
- Setting order quantities once and never reviewing them
See Bizowie in Action
Real screens from Bizowie, not mockups. Click any screen to enlarge.
Purchase orders with approvals, receiving, ASNs, and vendor invoices on one screen.
Every receipt, transfer, build, and quarantine move by SKU, lot, bin, and location.
Each work order carries its multi-level bill of materials, batches, and live on-hand quantities.
Bookings, open orders awaiting fulfillment, and inventory value at a glance.
Planning Purchasing and Production in Bizowie
Bizowie plans purchasing through MRP that is always up to date and reports purchasing requirements and shortages. Work orders can be created automatically or manually from sales activity and planned demand, and dependent work orders are created automatically for multi-level subassemblies. Production is scheduled forward or backward by priority and capacity, and every production event updates inventory, costing, and the general ledger at the same time. For the wider evaluation, see our manufacturing ERP software buyer’s guide and our comparison of ERP and MRP.
“From our first contact all the way through to our implementation, Bizowie has been a first class organization to work with… We strongly recommend the Bizowie software program.”
Alan Seymour — President, Cleveland Electric Labs
Frequently Asked Questions
What is lot sizing in MRP?
Lot sizing is the rule MRP uses to turn net requirements into planned order quantities. It determines how much is ordered or produced each time and therefore how often orders are placed and how much inventory is carried.
What is lot-for-lot ordering?
Lot-for-lot means ordering exactly the net requirement of each period. It carries no extra inventory and creates the largest number of orders, so it suits expensive items and items with a low order or setup cost.
What is the difference between fixed order quantity and period order quantity?
A fixed order quantity orders the same amount every time, at varying intervals. A period order quantity orders at a fixed interval and varies the amount to cover the requirements of that interval, which avoids leftover stock.
Which lot sizing method is best?
None is best for every item. Lot-for-lot fits high-value and make-to-order items, EOQ fits steady demand, and period order quantity fits uneven demand with a meaningful order or setup cost.
How does setup time affect lot size?
The higher the setup cost, the larger the lot that minimizes total cost. Reducing setup time lowers the cost per order, which makes smaller lots and lower inventory economical.
Bring Us Your Slowest-Moving Stock
Tell us how you set order quantities and plan production today. We’ll show you how Bizowie plans requirements, shortages, and work orders, and if we are not the right fit, we will tell you.
See how Bizowie would plan your materials
Tell us a little about your operation and we’ll reply with an honest assessment of fit, not a sales pitch.
- A real person reviews your submission and replies within one business day.
- No automated email sequences.
- If we’re not the right fit, we’ll tell you.
Prefer to talk?
Call (888) 635-2517, Mon–Fri, 9 AM–5 PM Eastern